The National Treasury has moved to dismiss reports suggesting that taxpayers could lose hundreds of billions following the cancellation of the High Grand Falls Dam Project.

In a statement on Wednesday, September 24, Treasury Cabinet Secretary John Mbadi clarified that the claims were unfounded and sought to reassure the public that the government faced no such exposure.

โ€œThe claim that taxpayers could lose up to Ksh317 billion from the cancellation of the High Grand Falls Dam Project is inaccurate. Under the Public Private Partnerships (PPP) framework, no obligation arises until a binding PPP Project Agreement approved by the PPP Committee is signed by project parties. We wish to confirm that no project agreement was signed for this project, and therefore no such liability exists for the government,โ€ he said.

Mbadi also addressed claims that the PPP Committee handling the project acted under influence of foreign interests.

Mbadi further pushed back against suggestions that the bidding process had already been concluded in favor of a particular consortium.

โ€œThe claim that GBM had already โ€œwon the tenderโ€ or that promises were made to foreign leaders are misleading. In 2017, the National Irrigation Board (NIB) invited bids for the High Grand Falls Dam Project under the Public Procurement and Asset Disposal (PPAD) Act, and not under the PPP framework,โ€ he further said.

Mbadi insisted that the decision to discontinue the project was made in accordance with the law, further emphasizing the governmentโ€™s commitment to accountability.

โ€œThe National Treasury affirms that the decision to terminate the High Grand Falls Dam Project under the PPP framework was lawful, transparent, and fully in line with the PPP Act.ย 

On how the decision to cancel the project was arrived at, Mbadi explained that the National Irrigation Authority, acting as the Contracting Authority, on January 30, 2023, submitted a proposal for the dam project to the National Treasury.ย 

The submission was a Privately Initiated Proposal from the GBM consortium, which included ERG International.ย 

The project was subsequently given preliminary approval on May 8, 2023, allowing it to progress to the development stage.

To guide this process, the National Irrigation Authority and the GBM consortium entered into a Project Development Agreement (PDA) in accordance with the PPP Act.ย 

The agreement outlined how the consortium would conduct the studies, the rules they were required to follow, and the legal requirements governing the project.

On March 14, 2024, the Contracting Authority submitted the Project Development Report (PDR) to the PPP Directorate, along with a request for a joint evaluation of the findings.

After the evaluation was completed, the Contracting Authority forwarded the finalized report to the PPP Directorate on July 31, 2024.

The report was later presented before the PPP Committee during a meeting held on July 2, 2025; the Committee deliberated on the findings and concluded that the project did not meet several statutory requirements.


Leave a Reply

Your email address will not be published. Required fields are marked *